Information about the construction work

On this page we share information from Akademiska Hus about the construction work in the near future.

Working hours 07:00-23:00
The project has permission to carry out weekend work, but this is only used when necessary.

Planned works during the period

The project is now entering a new phase, as we can finally begin to see real progress. In week 39, the prefabrication work will commence with the installation of pre-cast concrete inner walls. By the end of the year, we expect the entire building to be assembled, and at the beginning of next year, the façade panels will be installed.

Week 36 (1–5 September):

  • Casting of an exterior wall near the tree and Building E. (disturbance level: medium)
  • Prefabrication work with the inner wall panels. (disturbance level: medium)
  • Backfilling between the basement walls and the sheet piling. (disturbance level: medium)

Week 37 (8–12 September):

  • ing of an exterior wall near the tree and Building E. (disturbance level: medium)
  • Prefabrication work with the inner wall panels. (disturbance level: medium)
  • Backfilling between the basement walls and the sheet piling. (disturbance level: medium)

Week 38 (15–19 September):

  • ing of an exterior wall near the tree and Building E. (disturbance level: medium)
  • Prefabrication work with the inner wall panels. (disturbance level: medium)
  • Backfilling between the basement walls and the sheet piling. (disturbance level: medium)

Week 39 (22–26 September):

  • ing of an exterior wall near the tree and Building E. (disturbance level: medium)
  • Prefabrication work with the inner wall panels. (disturbance level: medium)
  • Backfilling between the basement walls and the sheet piling. (disturbance level: medium)

 

Estimated degree of disturbance in different parts of the school.

Green = low
Yellow = medium
Red = high

Image
Illustration of disturbances from the construction work in different parts of the School
Photo: Akademiska Hus

 

If you have questions

Questions about ongoing construction work that are affecting your work:

Campus Service Haga, service.handels@gu.se, 031 786 2160

Questions about the project at large:

Emma Deines, Project Manager, Strategic Project Management, University 91̽»¨, emma.deines@gu.se , +46 721-73 32 44

Questions and wishes regarding the communication about the project:

Maria ±·´Ç°ù°ù²õ³Ù°ùö³¾, Director of Communications, School of Business, Economics and Law, maria.norrstrom@handels.gu.se , 031-783 1247, 0709-226689